Cost of a restored / deviated Cheltenham to Kingham railway
Estimate that was referred to during June 2013 by Gloucestershire County Council was for a double track electrified railway used by a high frequency London commuter service.
But the restored Cheltenham – Kingham – Oxford railway would be single track and diesel operated
A more accurate comparison could be with the proposed re-opening of the railway between Bere Aston and Tavistock on the edge of Dartmoor, with a price tag of £150 million for 5.5 miles of single – track railway line beside a cycle way, to be operated with two coach diesel trains.
Using this cost per 5.5 miles plus cost of stations, structures and earthworks as a basis for calculation…
A “ball park figure” for the Cheltenham to Kingham scheme starts at £687 million plus cost of structures and earthworks
A recent comparison could be with the proposed re-opening of the railway between Stratford Upon Avon and Honeybourne, with a price tag of £228 million for 9 miles of single – track railway line at least partially beside a cycle way, to be operated with two or three coach diesel trains. Extensive tunneling is required at Stratford Upon Avon, extensive bridge repairs are needed along the route and track replacement is required between Long Marston and Honeybourne.
Using this cost per 9 miles plus cost of stations, structures and earthworks as a basis for calculation…
A “ball park figure” for the Cheltenham to Kingham scheme starts at £715 million plus cost of structures and earthworks.
Cheltenham to Kingham railway line 25 miles long maximum cost estimates
JUNCTIONS
Badgeworth (with NE SW Main Line) £25 million
Kingham (near station) £15 million (cost transferable between)
TOTAL £40 million
TRACK
Including any earth moving needed, fencing, clearance of foliage, surface preparation, drainage, track bed/ballast, all track (plain), Civil Engineering preparation to bridges, track side paths / farm access tracks where required, Level Crossings.
25 miles @ £27.48 million per mile = £687 million (Based on Tavistock Railway £150 million cost)
Including any earth moving needed, fencing, clearance of foliage, surface preparation, drainage, track bed/ballast, all track (plain), Civil Engineering preparation to bridges, track side paths / farm access tracks where required, Level Crossings.
25 miles @ £28.60 million per mile = £715 million (Based on Stratford to Honeybourne railway £228 million cost)
Passing loop and signaling for this at Andoversford
£30 million
Passing loop and signaling for this at Bourton – on - the - Water
£30 million
TUNNELS
New tunnel from Crippetts Lane to South of Charlton Kings Station (site of) behind C & G building, West of Cirencester Road.
£200 million
Repairs to re commission Sandywell Tunnel
£15 million
Works at Sandywell Park
£10 million
WORKS AT OR NEAR EAST PORTAL OF NEW TUNNEL WEST OF CIRENCESTER ROAD
Excavating deep cutting behind C & G building leading North East from tunnel portal to site of station, widening and reinforcing existing cutting face at site of station, removal of industrial units West of Cirencester Road.
£30 million
VIADUCT New 13 arch Dowdeswell viaduct £70 million
BRIDGES
Crossing the A46 at Chargrove major works would be required in form of a underpass to carry the road beneath the railway line and a bridge to carry rail line over road
£40 million.
Over bridges (carrying the railway over roads)
Cold Pool Lane Chargrove £10.7 million
Salperton - new bridge span £7 million
TOTAL £17.7 million.
Under bridges (carrying the railway under roads)
Crippetts Lane Cheltenham £10.7 million
Cirencester Road Cheltenham
£12 million
Little Herberts Road Cheltenham (dismantling the existing bridge and moving it to South)
£15.7 million
Notgrove East of station site £12 million
A424 East of station site Stow on the Wold £12 million
A429 North of Bourton – on – the – Water £20 million
TOTAL £49 million
STATION AREAS
All include Highway access, Civil Engineering Works needed on the formation at the locations, platform(s), lighting, shelters and track crossings via foot bridges at Andoversford and Bourton – on – the – Water.
Charlton Kings
Also remove excess trees and foliage, stabilize cutting faces, and provide a culvert for stream running along track bed.
£25 million
Andoversford
Bridges
Over bridge at Station Road Andoversford £15.7 million
Over bridge at A40 village bypass Andoversford £25 million
Also remove excess trees and foliage, attention as needed to the extant embankments of B&CDR and M&SWJR South of A40 village bypass, modifications to the embankment of M&SWJR near the crossing point of path leading from station road on A40, installation of solid retaining walls, use of path leading from Station Road as pedestrian access.
£35 million
Station £35 million
Bourton – on – the – Water
Also road access from A429 Fosse Way and associated works.
£15 million
Stow – on – the – Wold
Widen the cutting / formation beside existing station site to accommodate new station, removal of excess trees and foliage.
£10 million
POSSIBLE CONTINGENCY
Deep or complex excavations required at
Little Herberts South of Beeches Road / Ravensgate Road (to avoid extended gardens of houses),
Dowdeswell (two in filled cuttings),
Notgrove (widening the cutting beside existing station site, SSSI approaching station site).
Embankment Works required at
Dowdeswell(repair the embankment near to West portal of Sandywell tunnel),
Whittington (to provide a extended embankment from East portal of Sandywell tunnel to Station Road Andoversford),
Andoversford (to provide an embankment leading East from A40),
Bourton - on - the – Water (to provide an embankment leading East between extant track bed and A429 Fosse Way road).
Total I.D. Costs
£1,332,800,000 million if @ £53.312000 million per mile used
£1,360,800,000 million if @ £54,432,000 million per mile used.
LAND
Purchase of land for restored railway line: -
Purchase of 16 ½ miles of track bed of B & CDR between Little Herberts / Dowdeswell and Andoversford and Bourton on the Water (excluding Notgrove station site) and Bourton - on - the - Water and Kingham (excluding Stow - on - the - Wold station site and Chadwick Lakes Leisure site),
Purchase of ¼ mile of track bed of M&SWJR at Andoversford beside A40.
Purchase of land for deviated railway line: -
4 mile long strip of farm land South of Cheltenham, between Badgeworth Junction and East of Crippetts Lane
½ mile long strip of general amenity land South of Pine Holt at Andoversford,
½ mile long strip of general amenity land ex – railway land East of Station Road / South of A40 Village Bypass at Andoversford,
½ mile long strip of farm land beside Notgrove station site,
1 mile long strip of farm land to West of A429,
1 mile long strip of general amenity land to North of Industrial Estate at Bourton – on – the – Water.
½ mile long strip of farm land beside Stow – on- the - Wold station site,
1 mile long strip of farm land beside Chadwick Lakes leisure complex, and across an adjoining field
At approximately £30,000 per mile for 25 miles this works out at £750,000
Part 1 Compensation 1973 Land Compensation Act: -
In some cases owners of residential properties beside the railway line would be entitled to claim this.
The main areas in which residents would be entitled to claim would be around A46 at Chargrove, the Beeches Road / Ravensgate Road localities of Little Herberts, Pine Holt, Station Road and Huntsmans Reach roads in Andoversford, and the occupants of Stow – on – the – Wold station building.
-------------------------------------------------------------------------------------------------------------------------------------------------------------------
For more details see
https://www.facebook.com/people/Cheltenham-Kingham-Oxford-Railway-Line/61589601887319/
Create Your Own Website With Webador